Calibration Procedure

  • Find the ART case

* Remove the metal rods and L shaped alignment tool.

  • Assemble the two metal rods to create a single T-shaped alignment wand.

* Position the L shaped alignment tool in the center of the CAVE floor.  The bottom left point on the L will be the position of the origin (0, 0, 0).

  • From the rendernode, use the UltaVNC viewer to connect to the head node. We want to see Dtrack2 from within the CAVE to help with calbiration.

  • If Dtrack2 is currently measuring, then use the menu to stop measurement.
  • From Dtrack2's menu select: Calibration > Room

  • The settings that you want is 410mm wand length, and the coordinate system should say “Power wall”.

  • Then click the button labeled Calibrate.
  • Here is a video demonstration of how to wave the calibration wand within the CAVE.